Project Update | Racing Against Time and Ensuring Milestones! Suichuan Industrial Park No. 2 Wastewater Treatment Project Presses the "Fast-Forward Button" for Commissioning

2026-09-20




Recently, the Suichuan Industrial Park Second Wastewater Treatment Plant project undertaken by Tongyong Environmental Protection Group has achieved key progress! As a key infrastructure project for the park's green development, since construction began, the on-site construction team has seized the golden construction period, worked overtime, and carried out operations according to wall charts, making every effort to advance equipment installation and system commissioning. At present, all major equipment has been installed in place, and the project has fully shifted from the construction stage to the system linkage and process commissioning stage, sprinting toward the goal of early water commissioning and operation.



01

Refining Processes to Forge Hardcore Strength




The Suichuan Industrial Park Second Wastewater Treatment Plant has a total design capacity of 30,000 m³/d, with a near-term implementation capacity of 10,000 m³/d. The effluent is required to meet the Grade A standard of the Discharge Standard of Pollutants for Municipal Wastewater Treatment Plants (GB18918-2002).

In view of the complex composition and large fluctuations of wastewater in industrial parks, the project adopts a refined multi-stage combined process of "enhanced pretreatment + biochemical treatment + advanced treatment." The entire process is closely linked, with checks at every level, presenting four major technical highlights:



01

Fenton Advanced Oxidation: Efficiently Cracking the "Refractory Degradation" Challenge

A Fenton oxidation system is installed to precisely dose hydrogen peroxide, ferrous salts, and other chemicals. Through advanced oxidation, it efficiently decomposes refractory organic matter while simultaneously removing suspended solids, laying a good foundation for the stable operation of the subsequent biochemical system.

芬顿系统


02

MBBR Moving Bed Biofilm: Strongly Improving Biochemical Treatment Efficiency

The Bardenpho biochemical tank adopts the MBBR moving bed biofilm process, achieving a synergistic effect of "biofilm + activated sludge." It features high sludge concentration and strong resistance to shock loads, significantly improving nitrogen and phosphorus removal efficiency and effectively responding to influent water quality fluctuations.

生化池


03

High-Density Sedimentation Tank + Cloth Filter: Multiple Barriers to Ensure Stable Compliance

The advanced treatment section uses a high-density clarifier, with precise dosing of PAC, PAM, and powdered activated carbon to further remove suspended solids, color, and trace organic matter. It then undergoes fine filtration through cloth filters to ensure that the effluent stably meets the Grade A standard.



04

Full Coverage of Emergency Control: Simultaneous Advancement of Wastewater and Odor Treatment

The equalization tank is equipped with an emergency tank to effectively contain accidental wastewater and prevent exceedance shocks. Online monitoring rooms are set up at both the inlet and outlet to achieve real-time water quality monitoring. The plant is also equipped with a deodorization system, achieving full green environmental coverage.





02

Seizing the Schedule and Achieving Construction Speed




Facing the actual situation of a tight schedule, heavy tasks, and extensive cross-operation, the project department reversed the schedule and carried out operations according to wall charts, breaking down the overall goal item by item into weekly tasks and assigning them to individuals.


01

 "White + Black" and "Five + Two"

The construction workers voluntarily gave up rest time, implementing two-shift and rotating operations, with equipment installation advancing 24 hours a day without interruption.


02

Parallel Flow and Cross Construction

In response to concentrated equipment arrivals and labor shortages during peak installation, the project department scientifically dispatched operations, opened more work fronts, and promptly increased installation personnel and specialized teams for lifting, welding, and other tasks. Materials and equipment were "unloaded upon arrival and installed immediately," minimizing the time between processes.


03

Management Personnel Stationed On-Site to Lead Shifts

Project management personnel and technical backbones were stationed on-site throughout to lead shifts, strictly controlling installation quality and ensuring that both progress and quality met standards.





03

Fine Commissioning to Accelerate Commissioning Efficiency




Equipment installation and commissioning were planned simultaneously and seamlessly connected. The project department adhered to the principle of "commissioning one unit as soon as it is installed," and successively completed single-machine trial runs for each individual unit, comprehensively verifying equipment installation quality.

At present, the project is orderly advancing system linkage commissioning and process commissioning, laying a solid foundation for early water commissioning and operation and for bringing environmental benefits into play.




After the Suichuan Industrial Park Second Wastewater Treatment Plant is completed and put into operation, it will greatly enhance the park's wastewater collection and treatment capacity, effectively improve the regional water environment quality, further optimize the park's investment environment, and provide solid environmental support for the green and high-quality development of protecting clear waters and blue skies. 

With superb technology, a rigorous attitude, and efficient service, it will solidly carry out subsequent commissioning, operation support, and technical support, striving to build the Suichuan Industrial Park Second Wastewater Treatment Plant into a premium demonstration project. It will contribute greater strength to regional ecological civilization construction, green and low-carbon development, and beautiful park construction, and repay the trust and support of all sectors of society with tangible environmental benefits.